Planning Fundamentals

3x3E...yjf5
23 Jul 2023
41

What is the project schedule ?


It is an output which includes linked activities , milestones , durations and resources.
I t also contains delay between activities which defined as Lag
But the opposite of lag it called Lead ( Negative Lag )


Example :
Task B will start after 3 days from Task A finishing date


Now we will take a look for Leadin the above example : Task B & Task A have lead = 3days (another meaning Task A & Task B have -3 days Lag )

Dependency Relationships


Every schedule has many types of relationships between activities as following :

  • Finish to Start: The successor task cannot start until predecessor task has been finished
  • Start to Start : The successor task cannot start until predecessor task has been started
  • Finish to Finish: The successor task cannot finish until predecessor task has been finished
  • Start to Finish: The successor task cannot finish until predecessor task has been started